LunaNet Deliverables Program Plan
Source basis:
Tracks/LunaNet/deliverables.pdf
Mission
Deliver a full LSIS-AFS reference implementation covering spreading codes, FEC, frame building, baseband I/Q generation, decoding, parsing, integration, and final documentation.
Why This Plan Uses Gateway Sequencing
- LunaNet work spans DSP, coding theory, and interoperability; gateway partitioning limits defect blast radius.
- Early code-generation and framing correctness reduce wasted work in decoder and parser phases.
- Integration success depends on strict artifact and timing correctness (12-second frame, symbol/chip rates).
Competition Phases and Gateway Focus
- Foundation (April): Gateway 0 and Gateway 1
- Architecture plus spreading code generation
- Encoding (May): Gateway 2 and Gateway 3
- BCH/LDPC/CRC/interleaving and navigation frame assembly
- Signal (May-June): Gateway 4
- I/Q signal generation and modulation behavior
- Decoding (July): Gateway 5 and Gateway 6
- Sync detection, decoding, and message extraction
- Integration (August): Gateway 7 and Gateway 8
- End-to-end validation, interoperability, documentation, packaging
Minimum Viable Submission Gate (Pass/Fail)
Must include all:
- At least 12 PRN spreading codes generated correctly
- Complete 12-second navigation frame encoding
- I/Q signal files generated
- Validation tests for implemented features
- Setup/build instructions
Why this is critical:
- Failing the minimum gate yields zero evaluation regardless of partial progress.
Scoring Strategy (from deliverables)
- Correctness: 40
- Performance: 20
- Completeness: 20
- Code quality: 10
- Innovation/extras: 10
6-Person Ownership Model
- Engineer A: architecture/spec interpretation (LSIS volume + gateway standards)
- Engineer B: validation/performance owner (BER, sync, runtime budgets)
- Engineer C: interoperability and operations owner (exchange, runbooks)
- Developer A: code generation + encoding core
- Developer B: frame/message + signal generation core
- Developer C: decoding/parser + integration automation
Detailed Execution Docs
Why these companion docs:
- The program plan remains the high-level control view.
- Phase files and RACI isolate day-to-day execution detail and ownership accountability.
Gateway-by-Gateway Execution Priorities
- Gateway 0
- Freeze architecture, interfaces, and test strategy
- Gateway 1
- Validate all PRN code families against references
- Gateway 2
- Implement and verify BCH/LDPC/CRC/interleaving
- Gateway 3
- Assemble frame structure with exact timing and field allocations
- Gateway 4
- Generate standards-compliant I/Q outputs
- Gateway 5
- Decode with reliable sync and error-correction behavior
- Gateway 6
- Parse subframes and reconstruct timing fields
- Gateway 7
- End-to-end round-trip + interoperability + benchmark proof
- Gateway 8
- Submission-quality documentation and evidence package
Submission Readiness Milestones
- T-21 days: all core gateways (0-6) feature complete
- T-14 days: integration and interoperability stable
- T-7 days: documentation + evidence freeze candidate
- T-3 days: clean-room rerun and artifact signing
- T-1 day: submission checklist lock